Visual APS provides a material indicator column in the task panel to indicate to the planner, the availability of material for different types of job orders. The material indicator is updated whenever the calculate material function is run. This feature can be run manually when the calculate method is set to manual or when you open or refresh Visual APS when the calculate method is set to auto. Setting calculation method to manual or auto
Due to the complexities of material calculations, setting Visual APS to automatically recalculate can significantly slow down performance of Visual APS. Every time Visual APS is refreshed and opened, material calculations are performed. Therefore, it is recommended that the material calculation method is set to manual, so the user can control when recalculations will occur Recalculating material requirements
|