Views:

Rebuild
If you are not immediately seeing changes after updating your work unit properties, you may need to tick the rebuild check box on the work unit record


 

At any time, you can reset the shift against a resource.  When the resource has scheduled operations, you should decide how you wish to handle this before changing the resource.

When changing a shift against a resource you will be asked what to do with existing scheduled operations

Your choices are:

  • Nothing
  • Unschedule operations
  • Mark operations as possible errors

To assign a shift for a single resource

  1. Right click on the resource in the schedule board
  2. Click on Edit
  3. Select a different shift in the shift column
  4. Click Rebuild if a shift was previously assigned to the resource
  5. Click OK
  6. Select how you wish to manage scheduled activities
  7. Click OK

To assign a shift for multiple resources

  1. Click on the Home Menu
  2. Click on Work Units
  3. Select a different shift in the shift column
  4. Click Rebuild if a shift was previously assigned to the resource
  5. Click OK
  6. Select how you wish to manage scheduled activities
  7. Click OK


 

Functional Area: Detailed Scheduling
Comments (0)