Remove shift rule
To remove shift rules, right click on the day(s) in the calendar view and select Set to Default.

 

 

Changes can be made to multiple resources at a time. 

 

To change the shift for multiple resources

 
  1. Click on the Home Menu
  2. Click on Changes
  3. Tick the relevant sites and work centers
  4. Click on Add New
  5. Enter a value in the Shift change code field (i.e. shutdown)
  6. Under the timeline left click and drag to highlight the time (i.e. 00:00 to 00:00)
  7. Set the Activity Code to StdNonWorking
  8. Click OK
  9. Click on the heading Ungrouped from the Day Shift Changes task panel
  10. Right click on Shutdown
  11. Click Copy
  12. Select the dates (i.e 18th Dec to 1st Jan) by click/hold of left mouse button
  13. Right click on 1st January
  14. Click Paste
  15. Click OK
  16. Click Apply
  17. Click YES to rebuild the calendar
  18. Click Nothing
  19. Click OK


.

 