Views:

Zero Percentage
Set the percentage to zero if users should not report more than the previous operation.

A new validation setting has been provided to prevent users reporting operational quantity where the value exceeds the value reported in the previous Operation. (Run Time Task)

 

Where can I see the change?

 
  • Advanced Settings > Workbench > Elements > Workbench (Employee) > Functions > Schedule Task Settings > Reporting Options > General > Use Validation
  • Advanced Settings > Workbench > Elements > Workbench (Equipment) > Functions > Schedule Task Settings > Reporting Options > General > Use Validation
  • Advanced Settings > Workbench > Elements > Report Single > Functions > Report Single Settings > Use Validation
  • Advanced Settings > Workbench > Elements > Report Multiple> Functions > Report Multiple Settings > Use Validation