Task colours can be changed from the Designer Settings by selecting Settings from the Home Menu


Adding MRP suggested job orders to the production plan can be useful in determining potential loading in the long term. This is often referred to as rough cut capacity planning.

To auto schedule suggested job orders:

  1. Open the MRP Jobs tab under the task panel
  2. Select all the MRP Job Orders
  3. Right click and auto-schedule
  4. Return to the Schedule Board


Notice that MRP Suggested job order appear as a different colour in the Planning Board to make them stand out.



.


 