Task colours can be changed from the Designer Settings by selecting Settings from the Home Menu
Adding MRP suggested job orders to the production plan can be useful in determining potential loading in the long term. This is often referred to as rough cut capacity planning.
To auto schedule suggested job orders:
Open the MRP Jobs tab under the task panel
Select all the MRP Job Orders
Right click and auto-schedule
Return to the Schedule Board
Notice that MRP Suggested job order appear as a different colour in the Planning Board to make them stand out.