Views:

Planned Start/End
When job orders or operations are unscheduled, the planned start and end dates will revert back to the original dates

Scheduled job orders and operations are easily unscheduled.  There are a couple of ways to unschedule in Visual APS.

Method 1 

  1. Right click on the job order or operation in the task panel
  2. Click Unschedule or press delete on your keyboard
     

Method 2

  1. Highlight the operation on the schedule board
  2. Right click and select Unschedule or press delete on your keyboard
  1. Once unscheduled remember to save and publish your changes to the plan to update LYNQ  and Enterprise Resource Planning






 