Views:

Remember to refresh
If you create any new work unt in Enterprise resource planning, remember to refresh Visual APS before you run the import process

What to import
You don’t have to import all work units into Visual APS.  You can be selective during the import process

Rebuild
If you are not immediately seeing changes after updating your work unit properties, you may need to tick the rebuild check box on the work center record

 

 

You can select default propery values for your work unit during import from Enterprise Resource Planning.  Properties can also be updated post import.  Visual APS allows additional properties to be set against a work unit. Refer to the Advanced User Guide for Float resources and consumption settings.
 

 

Field

Infinite Resource

Indicates no limits to capacity - Resource type when using infinite capacity must be 'Not defined'

Resource Type

Type of resource

Default Resource Qty

Default No. of Resources

Float Resource Usage

Float Resources based on Type

Float Resource Usage Type

All/Less or Equal/Greater or Equal

Float Discrete Resource Usage

Float Resources based on min/max

Min Resource Consumption

Min no. of resources required

Max Resource Consumption

Max no. of resources required

Recommended Load Level (%)

Recommended load level percentage

Split Task Consumption (Min)

Minimum time during which a task can be started when splitting tasks

Split Task Interruption (Max)

Maximum time interruption when splitting tasks

Shift

Default shift

 

 


How to configure work unit properties

  1. From the Factory Explorer or Schedule board right click on the work unit
  2. Click Edit
  3. Change the properties as required
  4. Click OK


.

 

Functional Area: Resource Management

Related Articles (1)

Comments (0)